Home
/ Industrial & tertiary customer / New subscription
New subscription
Medium
Voltage and Medium Pressure
This type of subscription is considered in case
of connection to intermediate voltage or medium pressure network.
The
decision to allocate an IV or IP subscription
depends on the costumer needs and his distance
to the network.
Technical
constraints behind contracting a Medium Voltage
subscription are the requested power and the user
location with relation to the existing networks.
Medium Voltage
One-phase
17
kV + 7 % in isolated rural areas
Three-phase
30 kV ± 7%
Three-phase
15
kV ± 7% in certain Southern towns
Three-phase
10 kV ± 7% in certain
Central and Northern towns
How to apply ? Send
or submit a written application to your district
with a location
layout. The
district notes the distribution network features
on the project address as well as the location
and orientation of the station to be constructed,
and addresses to the customer either :
The estimated cost of electricity supply. the
list of firms approved by the Ministry of Equipment
which you can
consult to estimate your needs and construct
your substation.
What are the documents to be provided ? The firm
selected by the customer should submit to STEG,
for opinion, a technical file in three
copies involving : An
application form
A
building authorization or an occupation title
of the premise A
civil engineering layout (for cabin stations)
at 1/20th scale An
implementation layout at 1/1000th scale A
map at 1/10 000th scale A
descriptive memo indicating the different materials
used, their characteristics and their fitting.
Procedure for
approval of the technical file STEG studies the
supply line then sets the technical file and the
connection cost estimation. It sends the requester
a letter of estimate and submits the technical
files to the competent authorities of the
station for administrative enquiries.
The estimated charge remains valid for 3 months for a
connecting complying with the technical file submitted
to authorities for approval.
When
are the works performed? Further to authorities
approval of the line and payment of the due
charge, STEG submits an energy supplying contract
for customer signature. The substation construction
has to be performed by a firm selected from
the approved list according to the technical
file.